Construction [August 14th] Day Nine: Drone flyover, Grout outlet pipe, Construction Complete!
Construction [August 13th] Day Eight: Heavy rains last night - no action today.
Construction [August 12th] Day Seven: Rototilling for seed bed preparation
Construction [August 11th] Day Six: Complete wetted basin, add rock ledge habitat, complete French drain
Construction Day Five: French drain installation
Construction Day Four: Wetland bottom completed Drainage pipe begun.
Construction Day Three: Rain yesterday evening brought more water to pump out, initial grading has filled part of the pond, a second operator is quickening the progress.
Construction Day Two: Continued pond draining, honeysuckle grubbing, fish counting attempt,
Construction Day One: Pond draining